OD19022 – TN/751/Wafa/18 – Conection of New Gas Well A56 Flow Line to Sg-1 and Associated Facilities

الزبون

MOG

الموقع

Wafa Field – Libya

الحالة

 مكتمل

التصنيف

توصيلات الأنابيب

The whole series of LSTK Activities, inclusive of Site Survey, Project Management, Detailed Engineering, Material Procurement, Civil, Mechanical, Piping, Pipeline, Electrical, Instrumentation, Automation, Construction & Installation, Testing, Mechanical Completion, Pre-Commissioning, Commissioning (Under COMPANY Direction) and Assistance to COMPANY during the Start-Up of the Project, which are assigned to the CONTRACTOR by the COMPANY as per the LSTK CONTRACT.

SCOPE OF WORK

This Gas Pipeline would initially consist of 10 inch (API 5L GR X65, 14.3 mm thickness) for approx the first 4.3 km, and then be directly connected with a reducer to an 8 inch (API GR X65, 12.7 mm thickness) for approx the remaining 1.7 km. The total Pipeline length would be approximately 6 km.

صور المشروع

لنعمل معًا!

Interested in working with us? Contact us and our dedicated teams will be ready to assist you.

نموذج الاستفسار

RFQ

Maximum file size: 5.12MB