Project Update: Painting Campaign at Mellitah Complex

    |

    INTECH is pleased to share a new progress update from the Painting Campaign at Mellitah Complex, highlighting ongoing works on the Butane Tank (4E-220-TA-002B).

    Following the successful completion of the Propane Tank (4E-220-TA-001A) and Butane Tank (4E-220-TA-002A), our team continues to demonstrate exceptional commitment to quality, safety, and compliance in all aspects of the coating and surface protection works.

    Comprehensive surface preparation, blasting, and primer application have been successfully completed for the entire tank and associated staircase steel structures. The mid coat and final coat have also been applied in strict accordance with approved specifications and INTECH’s HSEQ policies and procedures, ensuring durability, performance, and aesthetic excellence.

    Currently, scaffolding dismantling is progressing smoothly and safely. Our scaffolding team is executing the activity with precision, coordination, and full adherence to safety protocols, maintaining INTECH’s high standards for worksite control and risk management.

    This milestone underscores INTECH’s unwavering dedication to Health, Safety, Environment, and Quality (HSEQ) principles and reflects our culture of continuous improvement, teamwork, and operational excellence.

    Intech management extends its sincere appreciation to all site personnel for their professionalism, discipline, and teamwork in delivering yet another successful phase of the Painting Campaign.