ORDER NO: 17033 PROVISION OF MANPOWER,TOOLS AND EQUIPMENT FOR DISMANTLING AND REMOVAL OF STEAM TURBINE INCLUDING SKID AT MELLITAH COMPLEX

PROVISION OF MANPOWER,TOOLS AND EQUIPMENT FOR DISMANTLING AND REMOVAL OF STEAM TURBINE INCLUDING SKID AT MELLITAH COMPLEX

SCOPE OF WORK: IT IS CLASSIFIED INTO TO 3 SECTIONS:

  • DISMANTLING OF MAIN ROOF COMPARTMENT INCLUDING THE STEEL STRUCTURE USING CRANE (220 TON)
  • DISMATLING AND REMOVAL OF STEAM TURBINE ELEMENTS INCLUDING THE SKID USING 220 TON CRANE
  • RE-INSTALLATION OF MAIN ROOF COMPARTMENT INCLUDING THE STEEL STRUCTURE USING 220 TON CRANE.

ACTIVITY WAS STARTED ON 28/07/2017

ACTIVITY WAS COMPLETED ON: 25/08/2017


Project ClientPROVISION OF MANPOWER,TOOLS AND EQUIPMENT FOR DISMANTLING AND REMOVAL OF STEAM TURBINE INCLUDING SKID AT MELLITAH COMPLEX